Steinaker Service Canal Enclosure Project

Reaches II and IIIA

Project Summary:  Beginning September 2022, the Uintah Water Conservancy District will be enclosing (piping) Reaches II and IIIA of the Steinaker Service Canal.  Reach I, or the southernmost 3+ miles of the canal, was piped in the fall of 2016 and spring of 2017.  Reaches II and IIIA will extend the pipeline to approximately 1300 South 1500 West, or an additional 2.82 miles.  With the ultimate goal of piping the entirely of the Steinaker Service Canal, and connecting the pipeline directly to Steinaker Dam, the current project represents a significant step and bold investment towards the Ashley Valley's future water security.  Because the Steinaker Service Canal will be operated as a hybrid system, with both open and piped sections, and because the canal's slope is extremely shallow, large diameter pipe is required to pass the needed flows.  When completed, the Steinaker Service Canal Enclosure Project - Reaches II and IIIA will be the largest diameter pressure pipe HDPE installation in the United States.  As such, specialized equipment is needed to accomplish the butt-fusion process (see video below).

Project Map: Map Icon                                                                                                            Project News Stories:

                                                                                                                                              Bureau of Reclamation - Piping the Steinaker Service Canal

Funding Partners:                                                                                                               Laying pipe in Service Canal

Design Engineer: Jordan Oyler, Bowen Collins & Associates

Project Manager: Mike Collins, Bowen Collins & Associates

Pipe Manufacturer: AGRU America

Pipe Supplier: ISCO Industries

Contractor: BHI, Project Manager - Mike Cottle

 

UWCD Logo     BOR Logo     BC&A Logo       ISCO Logo      BHI Logo     Agru Logo       

 

Pipe Arrival

53' lengths of 78" OD DR26 HDPE pipe arrive one truck at a time from AGRU America's facility in Georgetown, South Carolina.

Pipe Deliveries

BHI operators unload and stockpile pipe in staging areas along the Steinaker Service Canal.

Pipeline Elbows

15-degree fittings will be utilized to help match the pipeline to the canal alignment.

Use of 15 degree fittings

Four fittings required at first canal bend.

Tecnodue

The Italian-made Tecnodue fusing machine welds fittings to straight pipe.

Talon Welding Machine

First welds are accomplished with McElroy's Talon fusing machine.

ISCO Technicians

ISCO certified technicians operate the fusing equipment.

Two fusing machines making welds

Both styles of fusing machine welding pipe in staging area.

Screening Structure Demolition

The existing screening structure is demolished where the new project will connect to Reach I.

Pipeline Construction

Pipe trench preparations at 500 West road crossing.

Pipeline Construction

Pipeline is installed and partially back-filled at beginning reaches of the project.